求学快递网 考试题库
  1. 找试卷
  2. 专业标签
原创试题专区

《系统集成项目管理工程师》补充知识练习(五):专业英语

  • 试卷类型:在线模考

    参考人数:278

    试卷总分:113.0分

    答题时间:90分钟

    上传时间:2021-04-16

试卷简介

本套试卷集合了考试编委会的理论成果。专家们为考生提供了题目的答案,并逐题进行了讲解和分析。每道题在给出答案的同时,也给出了详尽透彻的解析,帮助考生进行知识点的巩固和记忆,让考生知其然,也知其所以然,从而能够把知识灵活自如地运用到实际中去。

试卷预览

1. Risk management allows the project manager and the project team not to()

A. eliminate most risks during the planning phase of the project

B. identify project risks

C. identify impacts of various risks

D. plan suitable responses

2. The project life-cycle can be described as ()

A.project concept, project planning, project execution, and project close-out

B. project planning, work authorization, and project reporting

C. project planning, project control, project definition, WBS development, and project termination

D. project concept, project execution, and project reporting

3. ()is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them. A PERT B AOA C WBS D PDM

A.PERT

B. AOA

C. WBS

D. PDM

4. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.

A. scope statement

B. activity list

C. project charter

D. project schedule

5. The Development of Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a ()

A. Project Scope Statement

B. Project Management Plan

C. Forecasts

D. Project Charter

最新推荐

    相关试卷

      微信扫码,立即支付

      微信扫描上方二维码

      ×
      平台更新说明
      更新版本:V.2 更新时间:2018年3月7日
      更新内容:
      1.修改若干Bug
      2.完善页面逻辑,提高做题体验度
      3.设立会员体系,为用户提供专属服务
      4.增加外部出卷功能,学校用户开通学校服务后即可拥有自己的试卷库和学生测试中心,可自主出题组卷,为本校考生组织考试